Similar Articles
NEW FOR THURSDAY: Morning Power Outage Affected 5,000
BERLIN -- Thousands were without power across a wide swath of northern...READ MORENEW FOR THURSDAY: Proposed Beach Music Festival Delayed Till 2014
OCEAN CITY – The much-anticipated High Tide Music Festival has b...READ MORENEW FOR THURSDAY: Of Rare Jetty Beach, Army Corps Says, ‘You’ll Probably Never See It Again’
OCEAN CITY -- A rare, if never-before-seen, anomaly appeared at the Oc...READ MORENEW FOR WEDNESDAY: Changes Looming For Ocean City Surf Beach Policies?
OCEAN CITY – Following in the footsteps of Ocean City’s bo...READ MORENEW FOR TUESDAY: Tip Averts Downtown OC Armed Robbery Last Night
OCEAN CITY -- Confidential information obtained by the Ocean City Poli...READ MORENEW FOR TUESDAY: Redevelopment Projects Proposed For Downtown Properties
OCEAN CITY – A few changes are on the horizon in the downtown ar...READ MORENEW FOR MONDAY: Worcester Casino Mulling Addition Of Table Games
SNOW HILL -- In the wake of a successful voter referendum for Maryland...READ MOREWorcester County News Briefs
SNOW HILL -- Discussed at Tuesday’s Worcester County Commissione...READ MORESalisbury Council Turns Away State Skate Park Grant
SALISBURY -- Citing environmental worries, a lack of cooperation with ...READ MOREMan Sentenced For Roommate Assault
SNOW HILL -- An Ocean City man arrested on first-degree rape and other...READ MOREOne Year Ago, Storm Ravaged Area Beaches
OCEAN CITY – This time last year Ocean City faced the worst storm in over a decade, as the dune system in many areas was destroyed but credited with saving millions of dollars of damage.
Last year’s storm hit on Nov. 13, 2009.“We lost all the east side sand fence, about a third of the dune and 300,000 cubic yards or so of sand,” City Engineer Terry McGean said.
Without a commitment to keep the beaches and dunes up to date, the storm could have caused more severe damages.
“Based on wave height and tide levels, we estimate that we would have sustained over $18 million in property damage from the storm if we had not had the project [beach replenishment],” McGean said.
This year’s beach replenishment project is repairing the damage caused from last winter’s harsh weather and preparing for upcoming years.
According to the town’s website, the beach areas completed to date is from 134th Street to the Delaware State line and 128th Street through 95th Street.
“We have had some weather delays, but overall the project is progressing nicely,” McGean said.
McGean estimates the beach replenishment project will be completed by the end of December, depending on weather conditions.
Last year’s storms may raise concern over the progress of the project, but the means behind the plan is to relieve storm anxiety.
“Since the whole purpose of the beach project is storm protection, I am always the least worried about storms right after the project,” McGean said. “That is when we have the most protection. I would much rather lose some fence and sand instead of lives or property.”
According to McGean, to date the project is estimated to have prevented over $256 million in damages for a total cost of just over $100 million.
“The project does just what it is intended to do,” McGean said. “It has been very successful.”