Similar Articles

NEW FOR WEDNESDAY: County To Seek Waiver For Traffic Light At Troubled Spot

SNOW HILL -- Following a heated meeting between the State Highway Admi...READ MORE

NEW FOR FRIDAY: Wacky Crime Stories From 2012

OCEAN CITY -- Throughout the course of each year, hundreds of criminal...READ MORE

Accident Claims Life Of Local Man

BERLIN -- A local man was killed Wednesday in a two-vehicle accident a...READ MORE

Wicomico Audit Confirms Expenses Below Budget

SALISBURY – Wicomico County’s annual audit this year revea...READ MORE

Compromise Reached To Protect Atlantic Menhaden

OCEAN CITY -- Federal fisheries management officials last week took an...READ MORE

Downtown Group Keeps Inlet Lights Goal In Sight

OCEAN CITY – Although the holiday season will come to an end nex...READ MORE

Downtown Restaurant Building Demolition Near

OCEAN CITY – The Fat Daddy’s restaurant building on S. Bal...READ MORE

Some Salisbury Boards Struggling With Participation

SALISBURY -- A few commissions in Salisbury have had trouble operating...READ MORE

Spotlight Put On ‘Silent Giants’ At OC Open House

OCEAN CITY -- Residents and visitors are invited to start off the New ...READ MORE

More Work Needed On Airport Runway To Pass Inspection

8/24/2012 | By Joanne Shriner, Staff Writer

OCEAN CITY – A failed inspection of a recent runway project at the Ocean City Municipal Airport is currently being addressed and the repaving is expected to be completed next month.

According to Ocean City Public Works Director Hal Adkins, the scope of the runway project was expansive, including milling the runway and underground excavation for electrical work to the installation of navigational aids, stormwater management and perimeter fencing.

Construction began in May. The contract included a 90-day work period having the project be wrapped up in late-July.

The town’s airport consultant of record is Delta Aviation, which designed the project and provided on-site inspections as required by the Federal Aviation Administration (FAA).

“The final surface level of pavement on the runway has failed relative to inspection,” Adkins said on Monday. “Some of the grades were wrong and some of the compaction tests failed … the runway is not back open yet.”

Adkins furthered that there is a documented paper trail that started in late July between Delta Aviation and the contractor that the contractor has until Aug. 24 to provide Ocean City engineers a schedule indicating how they are going to correct the problem and they have until Sept. 4 to mobilize and beginning addressing it.

“They are probably going to have to mill the surface off down about an inch and re-lay a new surface,” Adkins said. “It is unfortunate that the project didn’t wrap up late-July and everything was perfect, and it has been an inconvenience to the airport in the interim but I am hoping to have a resolution come from the contractor by the end of this week on what they are going to do to correct the problem.”

The correction will have no effect to the funding of the project. Any or all corrective measures are the responsibility of the contractor. There will be no additional expenditure funds on behalf of the town or FAA.

The airport has two runways and the runway under construction is the north-south runway, indicator number 02/20, also known as the cross-wind runway.

Adkins reported a review of the airport’s fuel sales from May through July has shown that the reconstruction has not negatively impacted the airport’s revenue stream.

“I want everyone to realize that the issue is the fact that the final surface is not compliant, the rest of the project went fine,” he said.

Adkins estimated if all goes as planned work will be completed by Sept. 15.