Similar Articles
NEW FOR THURSDAY: Indian Sculpture’s Future In Ocean City Unclear
OCEAN CITY -- With restoration funding uncertain, the future of the la...READ MORENEW FOR THURSDAY: School Safety Plan Includes 13 Resource Officers; Positions Will Need Special County Funding
SNOW HILL -- A new Safety Action Plan for Worcester County’s pub...READ MORENEW FOR WEDNESDAY: Beer, Bean Can Assault Suspect In Hot Water Again
OCEAN CITY -- An Ocean City woman, arrested twice within a few hours t...READ MORENEW FOR WEDNESDAY: County Approves New ‘Flagship’ Liquor Store On Route 50; West OC To Close Immediately; Berlin Store Likely Later
SNOW HILL -- The county-run Department of Liquor Control (DLC) asked a...READ MORENEW FOR TUESDAY: Four Arrested In Worcester Now Headed To Federal Court
BERLIN - Four men arrested and charged initially with drug distributio...READ MORENEW FOR MONDAY: Komen Race For The Cure Eyes April Return To OC
OCEAN CITY -- The boards in Ocean City will once again be flooded with...READ MORECounty Prepared To Handle Disasters, Staff Assures
SNOW HILL -- Hurricane season does not begin until June, but the Worce...READ MORECity Okays Employee Pay Study
SALISBURY – The City of Salisbury will receive an outsider’...READ MORECouncil Tables Elected Officials’ Travel Policy Changes
SALISBURY – A discussion over elected officials’ travel ex...READ MOREO’Malley Makes Big Push For Wind Energy Legislation
ANNAPOLIS -- Governor Martin O’Malley this week made his first b...READ MORECannery Village Hopeful For June Start
BERLIN - The Cannery Village workforce housing project should be under construction by the end of June if all goes well.
Frank Gunion, president of the Berlin Community Development Corporation, said he would know more about the next step at the end of next week when he expects a decision from the state on a necessary community development block grant.
'One thing's that hanging fire is the continuation of the block grant or not,' said Gunion. 'If the block grant is reaffirmed once again, we should be ready to draw a grading permit from the town within the month.'
Supporters have been working on the workforce housing project for four years.
Previous plans made last fall to dig the first shovel of dirt over the winter stalled over funding issues.
The Cannery Village workforce housing project is attempting to knit together support from several different sources to create a small community of green, affordable houses for local residents who cannot afford the high property costs in northern Worcester County.
One consequence of the multiple partners and supporters for the Cannery Village project is limits on funding, which require that work begin by the end of June.
'Other grants we have are keyed into June 28. We have to start by then,' Gunion said.
The workforce housing project has done the proper due diligence, from stormwater to wetlands plans, as well as the necessary engineering. However, the town of Berlin still needs to give final approval to the project.
The most optimistic date for completion of the first 10 homes, the first phase, is probably late fall, Gunion guessed.
Bureaucracy has at times held the project back, with seven different government agencies involved. Gunion put that down in part to the new approach of the workforce housing initiative, which is using a pioneering public-private partnership to pursue the Cannery Village community.
'It's a new way of doing this project. It's the only way they're going to happen,' said Gunion.
For-profit projects cannot afford to sell green houses at an reasonable price. High-end prices are the norm for that type of residence.
'There is very little workforce housing being built or for sale,' said Gunion.